Tweed Heads Hotel Lift Pit
Emergency lift pit waterproofing for a busy hotel experiencing repeated lift failures due to water.
Tweed Heads
5 days
Project Photos Coming Soon
Project Overview
About This Project
A Tweed Heads hotel was experiencing repeated lift failures due to water in their lift pit, causing significant guest inconvenience and safety concerns. Our team responded quickly, completing the waterproofing works within a week to minimise disruption to hotel operations. The negative-side waterproofing solution has kept the pit dry ever since.
Project Challenges
Urgent timeline for busy hotel
Active water ingress during works
Minimising lift downtime
Results Achieved
Lift returned to service in 5 days
No further water issues reported
Full NCC compliance achieved
Services Provided
Lift Pit Waterproofing
Polyurethane Crack Injection